Skip to content

Mission

Chiller Short-Cycling

The chilled water plant serving the process hall is tripping on low pressure, restarting, and tripping again — about twelve times an hour since first thing this morning. Chilled water flow temperature is climbing and two process lines will have to come off if it reaches 12 °C. The contract refrigeration engineer can be on site in four hours and wants to know whether to bring gas.

CHW-01 · UTILITIES

Elapsed 00:00

Machine
CHW-01
State
LOCKOUT / LP
Suction
2.1 bar
Discharge
12.4 bar
CHW flow temp
9.8 °C
CHW return
20.9 °C
Setpoint
6.0 °C
Trips
12 / hour

Investigate

Information

Controls & feedback

Mechanical

Intervention

Action log

0 entries

No actions logged

Every investigation costs time. Choose the order deliberately — you are scored on it.

Submit diagnosis

You can call it at any point. Submitting ends the mission and is scored on the evidence behind the answer, not only on the answer.

Candidate diagnoses